Amendment 5 pushes bid date back to Thursday, July 30th @ 2pm.

Amendment 4 answers RFIs, provides Gas Piping Spec 23 11 20, and revised drawing.

Amendment 3 answers RFIs and revises spec section 23 07 00 and 26 20 00.  Bid date and time remains the same.

Amendment 2 provides answers to RFIs and site visit sign in sheet

Amendment 1 provides site visit information

Please provide pricing per Pricing Sheet

Site Visit: Will be scheduled via amendment  Per amendment #1, site visit will be Thursday, June 25th @ 10am.  Meet at HP135.

Special Scheduling: Manhole work between “C” Street and Building HP250 shall be completed at the start of the project timeline (Refer to drawing sheet CU103).

Requests for Information (RFIs): Cut off for RFIs is Thursday, July 2nd @ 12pm.  Please send RFIs to estimating@ecmechanical.biz, dautry@ecmechanical.biz, or msanders@ecmechanical.biz.

Proposal Acceptance Period: 60 Days from receipt of award.

Liquidated Damages $880.00 for each calendar day of delay until work is completed or accepted