Amendment 6 extends bid date to Friday, 3/20

Amendment 5 extends bid date to Friday, 3/13

Amendment 4 only applicable to GC’s

Amendment 3 answers RFIs

Amendment 2 provides site visit information.

Amendment 1 answers RFI’s

***See Price Schedule for Specific Bid Items-Buildings Bid Seperately***

Site Visit: Will be scheduled via an amendment

Requests for Information (RFIs): Cut off for RFIs is Friday, February 20th @ 3pm.

Proposal Acceptance Period: 60 Days from receipt of award.

Liquidated Damages $880 for each calendar day of delay until work is completed or accepted