Amendment 3 issued. Bid date remains the same. Answers RFIs/PPIs. Issues new Specs and Drawings.
Amendment 2 issued. Pushes bid date back to April 28th. Please have pricing by close of business on Friday 4/24. Provides new Price Proposal Form and answers RFIs/PPIs.
Amendment 1 provides a revised Price Schedule
Site Visit: No Site Visit Scheduled
Requests for Information (RFIs): Cut off for RFIs is 14 calendar days prior to the proposal due date
Proposal Acceptance Period: 120 Days from receipt of award.
Liquidated Damages $35,391.79 for each calendar day of delay until work is completed or accepted