Site Prep for Ultrasonic Degreaser, B133

Site Visit: Tuesday, May 5th @ 10am.  Meet at FEAD Office, Building 87. Requests for Information (RFIs): Cut off for RFIs is Tuesday, May 12th by 12pm. Liquidated Damages $318 for each calendar day of delay until work is completed or accepted

R149 Modifications for MSAT, Bldg 4845, VMUT-2

Site Visit: Wednesday, May 6th @ 9am.  Meet at FEAD Office, Building 87. Pre-Proposal Inquiries (PPIs): Cut off for PPIs is Tuesday, May 19th by 1pm.  Must be submitted on Master PPI Form. Proposal Acceptance Period: 90 Days from receipt of...

P995 Composite Repair Facility

Amendment 6-Bid date remains the same.  Answers RFIs/PPIs.  Removes CUI from P993 Submittal Register, Division 1 Specifications, and Civil and Landscaping Drawings. Amendment 5 answers RFIs/PPIs. Amendment 4 issued.  Bid date pushed back to May 20th.  Please have...

Replace Elevator, DLA Distribution, B159

Amendment 2 gives GC bid delivery instructions Site Visit: Monday, March 2nd @ 10am.  Meet at B-87. Requests for Information (RFIs): Cut off for RFIs is Monday, March 9th by 12pm Proposal Acceptance Period: 60 Days from receipt of award. Liquidated Damages $531 for...