***Amendment 1 sets up site visit for Wednesday, August 27th @ 10:15am. Instructions included in amendment*** Site Visit: To be determined per amendment. Requests for Information (RFIs): Cut off for RFIs is 14 days prior to proposal date. Proposal Acceptance Period:...
by Gary Ferguson | Jul 9, 2025
by Gary Ferguson | Jun 30, 2025
***Amendment 4 pushes bid date back to Tuesday, August 5th*** ***Amendment 3 answers RFI’s, provides revised M602 drawing, and revised plumbing spec*** ***Amendment 2 add revised pricing sheet*** Site Visit: Tuesday, July 8th @ 1pm. Meet at BEQ BB250. Requests...
by Gary Ferguson | Jun 19, 2025
***Amendment 4 provides info on sump basin and revises detail A3 on drawing P-501*** ***Amendment 1 provides new 22 00 00 Plumbing Specification*** Site Visit: Monday, June 23rd @ 8am. Meet at FEAD Office. Requests for Information (RFIs): Cut off for RFIs is Friday,...