Amendment 3 answers RFIs, issues revised drawings, add specification section, and pushes bid date back to Tuesday, September 1st.

Amendment 2 answers RFIs, issues revised Mechanical Drawings, and pushes bid date back to Wednesday, August 26th.

Amendment 1 answers RFIs.  Bid date and time remains the same.

Please provide pricing per Price Proposal Form

Site Visit: Tuesday, July 28th @ 8:30am.  Meet at the FEAD Office.

Requests for Information (RFIs): Cut off for RFIs is Friday, August 7th @ 12pm.  Please use RFI/PPI form below.  Please send RFIs to estimating@ecmechanical.biz, dautry@ecmechanical.biz, and msanders@ecmechanical.biz.

Proposal Acceptance Period: 90 days.

Liquidated Damages $1,326 for each calendar day of delay until work is completed or accepted