Amendment 1 answers RFIs on the ERU.  Bid date and time remains the same.

Site Visit: Tuesday, July 21st @ 1pm.  Contractors are to meet in front of RR155.

Special Scheduling: Facility will remain in operation during the entire construction period.  The contractor shall conduct his operations so as to cause the least possible interference with normal operations of the facility.

Requests for Information (RFIs): Cut off for RFIs is Friday, August 7th @ 12pm.  Please send RFIs to estimating@ecmechanical.biz, dautry@ecmechanical.biz, and msanders@ecmechanical.biz.

Proposal Acceptance Period: 60 Days from receipt of award.

Liquidated Damages $220.00 per calendar day