Amendment 5 pushes bid date back to Thursday, July 30th @ 2pm.
Amendment 4 answers RFIs, provides Gas Piping Spec 23 11 20, and revised drawing.
Amendment 3 answers RFIs and revises spec section 23 07 00 and 26 20 00. Bid date and time remains the same.
Amendment 2 provides answers to RFIs and site visit sign in sheet
Amendment 1 provides site visit information
Please provide pricing per Pricing Sheet
Site Visit: Will be scheduled via amendment Per amendment #1, site visit will be Thursday, June 25th @ 10am. Meet at HP135.
Special Scheduling: Manhole work between “C” Street and Building HP250 shall be completed at the start of the project timeline (Refer to drawing sheet CU103).
Requests for Information (RFIs): Cut off for RFIs is Thursday, July 2nd @ 12pm. Please send RFIs to estimating@ecmechanical.biz, dautry@ecmechanical.biz, or msanders@ecmechanical.biz.
Proposal Acceptance Period: 60 Days from receipt of award.
Liquidated Damages $880.00 for each calendar day of delay until work is completed or accepted