Amendment 7 answers RFIs and pushes bid date back to Wednesday, August 5th @ 1pm.
Amendment 6 pushes bid date back to Friday, July 31st @ 1pm.
Amendment 5 pushes bid date back to July 27th, answers RFIs, provides new Gas Spec 23 11 20, and revised drawings
Amendment 4 pushes bid date back to July 20th, answers RFIs, and revises spec sections 23 07 00, and 26 20 00.
Amendment 3 answers RFIs. Bid date and time remains the same.
Amendment 2 provides updated Proposal Pricing Sheet.
Amendment 1 provides site visit information.
Please provide pricing per Pricing Sheet
Site Visit: Will be scheduled via amendment Per Amendment #1, site visit will be Tuesday, June 23rd @ 10am. Meet at FC555.
Requests for Information (RFIs): Cut off for RFIs is Monday, June 29th @ 12pm. Please use PPI form and send to estimating@ecmechanical.biz, dautry@ecmechanical.biz, or msanders@ecmechanical.biz.
Proposal Acceptance Period: 60 Days from receipt of award.
Liquidated Damages $880.00 for each calendar day of delay until work is completed or accepted