Amendment 9 deletes duplicate specs & drawings from Amendment 8.

***Amendment 8 pushes bid date back to March 13th.  Adds specifications, drawings, and continuation sheets.***

Amendment 7 add specifications and drawings

***Amendment 6 pushes bid date back to March 10th.  Amendment 7 will ensue.***

Amendment 4 pushes bid date back to March 3rd, provides answers to PPI’s and revises Price Proposal Form

Amendment #3 answers RFIs and provides revised Price Schedule.

***See Price Schedule for Specific Base Bid and Options for each Project***

Site Visit: Wednesday, February 4th from 9am-12pm. ***Per Amendment #1-Site visit rescheduled for Monday, February 9th @ 1pm.***

Requests for Information (RFIs): Cut off for RFIs is 14 days prior to proposal date.  Use PPI Form Below.

Proposal Acceptance Period: 120 Days from receipt of award.

Liquidated Damages $3,057.22 for each calendar day of delay until work is completed or accepted