by Gary Ferguson | Nov 18, 2024
Site Visit: Wednesday December 4th @ 9am. Meet at Building 87, FEAD Office. Requests for Information (RFIs): Cut off for RFIs is Friday, December 6th @ 9am. Proposal Acceptance Period: 90 Days from receipt of award. Liquidated Damages $316.00 for each calendar day of...
by Gary Ferguson | Jul 2, 2024
Site Visit: Monday July 8th @ 10am @ FEAD Office, Building 87. Requests for Information (RFIs): Cut off for RFIs is Monday, July 29th @ 9am. Proposal Acceptance Period: 90 Days from receipt of award Liquidated Damages $88.00 for each calendar day of delay until work...
by Gary Ferguson | Aug 1, 2023
Special Scheduling Requirements: Demolition of buildings HP305, HP306, and HP309 must be completed before the renovation of BEQ HP165. ***See Pricing Sheet for specific pricing instructions.*** Site Visit: Wednesday, August 9th @ 2pm at HP165. Requests for Information...
by Gary Ferguson | Jul 31, 2023
Site Visit: None Requests for Information (RFIs): Cut off for RFIs is Thursday, August 10th by 5pm. Proposal Acceptance Period: 60 Days from receipt of award Liquidated Damages: $880 for each calendar day of delay until work is completed or...
by Gary Ferguson | Jul 6, 2023
***See bid form for pricing instructions.*** Site Visit: Wednesday, July 12th @ 8am. Meet at FEAD Office, Building 87. If attending site visit, names must be submitted to Erika Bishop and Linda Clark prior to COB July 7th. Requests for Information (RFIs): Cut off...
Recent Comments