by Gary Ferguson | Jan 19, 2026
Prebid Site Visit: Tuesday January 27th @ 2pm. Meet at TA Loving’s jobsite trailer behind Legacy Hall. Requests for Information (RFIs): Cut off for RFIs is Wednesday, February 18th @ 5pm. Liquidated Damages $100.00 for per bed per day until work is completed or...
by Gary Ferguson | Dec 18, 2025
***1-14-26-Bid date extended to 2/13/26. Please provide quotations by 12pm on 2/12/26. Duke Energy is expected to receive and distribute 90% drawings by Friday, January 23rd. Once 90% drawings are received, we will upload and notify bidders via email.*** ...
by Gary Ferguson | Dec 18, 2025
Amendment 4 pushes bid date back to Friday, January 23rd @ 12pm and provides a Revised Bid Form. Amendment 3 answers RFIs and Revised Bid Form Amendment 2 pushes bid date back to Wednesday, January 21st. Site Visit: Wednesday, December 31st @ 9:30am. Contractors...
by Gary Ferguson | Dec 16, 2025
Addendum 3 answers RFI’s, adds Boiler Venting to Specs, Adds Lab Waste Sampling Ports to Plumbing, and provides Bid Letting Site Plan, and Room Location. Addendum 2 answers RFI’s, adds Pre-Bid Presentation and Sign-In Sheet, and adds BIM Execution Plan...
by Gary Ferguson | Sep 18, 2025
Amendment #8 includes updated Davis Bacon Wage Scale and pushes bid date back to 1/14/26. Please provide pricing by close of business on 1/13/26. Amendment #7 answers PPIs. Bid date remains the same. Amendment #6 answers PPIs, provides new Price Proposal Form, and...