BEQ Repair AS4212

***Government sent out a revised Amendment 12*** ***Amendment 12 provides a new Bid Proposal Form*** ***Amendment #11 answers RFI on Pre-Insulated Piping. Bid date remains the same*** ***Per Amendment #10-Bid date moved to Thursday, August 14th*** ***Per amendment...

Design Wing Relocation, Building 1005

Amendment 7-Incorporated PPI Responses & Issued Revised Drawing M101 Amendment 6-Bid Date pushed back to Wednesday, April 9th.  Due to this being a seed project, please forward pricing no later than 2pm on Tuesday, April 8th.  Revised specifications and drawings...

Site Prep for Ultrasonic Degreaser, B133 FRCE

Site Visit: Wednesday December 4th @ 9am.  Meet at Building 87, FEAD Office. Requests for Information (RFIs): Cut off for RFIs is Friday, December 6th @ 9am. Proposal Acceptance Period: 90 Days from receipt of award. Liquidated Damages $316.00 for each calendar day of...

Repair BEQ HP165

Special Scheduling Requirements: Demolition of buildings HP305, HP306, and HP309 must be completed before the renovation of BEQ HP165. ***See Pricing Sheet for specific pricing instructions.*** Site Visit: Wednesday, August 9th @ 2pm at HP165. Requests for Information...

TC601 Repair by Replacement

Site Visit: None Requests for Information (RFIs): Cut off for RFIs is Thursday, August 10th by 5pm. Proposal Acceptance Period: 60 Days from receipt of award Liquidated Damages: $880 for each calendar day of delay until work is completed or...