***Amendment 4 provides info on sump basin and revises detail A3 on drawing P-501***

***Amendment 1 provides new 22 00 00 Plumbing Specification***

Site Visit: Monday, June 23rd @ 8am.  Meet at FEAD Office.

Requests for Information (RFIs): Cut off for RFIs is Friday, June 27th @ 9am.

Proposal Acceptance Period: 60 Days from receipt of award.

Liquidated Damages Phase 1 is $3,016 per calendar day, Phase 2 is $2,062 per calendar day

Special Scheduling Requirements: CCD #1 or Phase 1 is 255 days after contract award.  This includes CLIN 0001AA and CLIN 0002 and any other related effort to construct the concrete slab and complete utility stub-ups, to include any permitting, plans, coordination etc.  CCD #2 is 555 days after contract award.  It includes all remaining contract work including fencing, other civil efforts, etc.