by Gary Ferguson | Jun 29, 2022
Site Visit: Wednesday, July 6th @ 9am. Meet at the FEAD Office, Building 87. Requests for Information (RFI): Cut off for RFIs is Saturday, August 6th @ 9am. Proposal Acceptance Period: 120 Days from receipt of award Liquidated Damages: $3,235 for each calendar day of...
by Gary Ferguson | Mar 10, 2022
Site Visit: None scheduled at this time. Pre-Proposal Inquiries (PPI): PPIs must be submitting in writing via Pre-Proposal Inquiry form. Proposal Acceptance Period: 120 Days from receipt of award Liquidated Damages: $1,200 for each calendar day of delay until work is...
by Gary Ferguson | Jan 26, 2022
Pre-bid site visit will be Wednesday, February 9th @ 2pm. Meet @ BEQ HP115. Cut off for RFIs is Wednesday, February 16th @ 3pm. Proposal Acceptance Period: 60 days
by Gary Ferguson | Jan 14, 2022
Special Scheduling Notes: Total contract performance shall be 330 days consisting of 2 separate Notice of Proceeds. Ninety days following the 1st Notice to Proceed will be allowed for submittal approval, equipment ordering and delivery only. No on-site work will be...
Recent Comments