***2/17-Government has just issued Amendment 12 pushing bid date back to Tuesday, March 10th @ 2pm. Please send revised quotations back by Monday, March 9th @ 12pm.***
***2/16 @ 8:12am-Please provide pricing by 3pm today. All GC’s have requested pricing by close of business today. We would like to comply with the requests. If you have any issues, please respond to Donnie or Cagie.***
Amendment 11 answers PPIs. Bid date remains the same.
Amendment 10 updates CMMC standard for seed project to Level 1 (self). Bid date remains the same.
Amendment 9 extends bid date to Tuesday, February 17th.
Amendment 8 provides updated Davis Bacon Wage Scale and answers PPIs. Bid date remains the same.
Amendment 7 extends bid date to Wednesday, January 28th. Please provide pricing by Tuesday, January 27th @ 2pm. Amendment also answers PPI’s, and provides Civil Drawings revisions.
Amendment 6 extends bid date to Wednesday, December 10th. Please provide pricing by Tuesday, December 9th @ 2pm.
Amendment 5 extends bid date to Wednesday, November 26th
Amendment 4 changes bid date to Wednesday, November 12th, answers PPI’s, and provides specs and drawings revisions
Amendment 3 changes bid date to Tuesday, October 28th, answers PPI’s, updates Price Proposal Form, and provides specs and drawings revisions
Amendment 2 provides Site Visit Log, and answers PPI’s
***Amendment 1 sets up site visit for Wednesday, August 27th @ 10:15am. Instructions included in amendment***
Site Visit: To be determined per amendment.
Requests for Information (RFIs): Cut off for RFIs is 14 days prior to proposal date.
Proposal Acceptance Period: 120 Days from receipt of award.
Liquidated Damages $2,457.95 for each calendar day of delay until work is completed or accepted