Amendment 7-Incorporated PPI Responses & Issued Revised Drawing M101
Amendment 6-Bid Date pushed back to Wednesday, April 9th. Due to this being a seed project, please forward pricing no later than 2pm on Tuesday, April 8th. Revised specifications and drawings also included in amendment 6.
Per amendment 1-Site visit will be Thursday, March 6th @ 1pm. See Site Visit Information and Site Visit Participation Forms for more information
Site Visit: To be determined per amendment.
Requests for Information (RFIs): Cut off for RFIs is 10 days prior to the proposal due date.
Proposal Acceptance Period: 120 Days from receipt of award.
Liquidated Damages $547.00 for each calendar day of delay until work is completed or accepted